Skip to content
Deger ConstructionDEGERConstruction

Projects & references

Completed sites

Water mains, irrigation systems and pump installations across Bulgaria.

Completed sites from our practice — water mains, special chambers and trenchless crossings across Bulgaria. The gallery is updated as new sites are delivered.

Pump connection reconstruction — Merichleri3

Pump connection reconstruction — Merichleri

Merichleri

Reconstruction of a pump connection in Merichleri — rebuilding the pipework manifold from PE pipes and fittings with shut-off valves around the pump. The site is in progress.

  • Reconstruction of the pump's pipework manifold
  • PE pipes, fittings and electrofusion joints
  • Shut-off valves around the pump
  • The site is in progress
Water mains for 9 sprinkler systems — Elit 20958

Water mains for 9 sprinkler systems — Elit 2095

Elit 2095

The start (9 September) of our most ambitious project of the year — water mains for 9 sprinkler irrigation systems for Elit 2095, with PE pipes from DN125 to DN400. In the first 10 working days, 3695 m of mains have been laid. The project is in progress.

  • Water mains for 9 sprinkler irrigation systems
  • DN400 PN10 — 2408 m
  • DN400 PN6 — 800 m
  • DN315 PN10 — 1949 m
  • DN250 PN10 — 284 m
  • DN200 PN10 — 3051 m
  • DN160 PN10 — 594 m
  • DN125 PN10 — 594 m
3300 m Ø250 irrigation main with hydrants — Dimchevo10

3300 m Ø250 irrigation main with hydrants — Dimchevo

Dimchevo

Construction of a new irrigation main at Dimchevo with a water intake from a reservoir (the Mandra reservoir) — 3300 m of Ø250 HDPE pipe with 27 hydrants for hose-reel irrigation machines, 10 air-valve shafts and 10 drain (washout) shafts. The site is complete.

  • Irrigation main from Ø250 HDPE pipe — 3300 m
  • 27 hydrants for hose-reel machines
  • 10 air-valve shafts
  • 10 drain (washout) shafts
  • Water intake from a reservoir (Mandra)
Tying Valley pivots into the main — Katrig ET7

Tying Valley pivots into the main — Katrig ET

Katrig ET

Connecting Valley centre-pivot machines to the supply main for Katrig ET — foundation, riser with shut-off valves and the tie-in to the main. The pivots are ready to irrigate as soon as the pump arrives.

  • Tying Valley centre pivots into the main
  • Tie-in at the pivot centre with shut-off valves
  • Electrofusion and butt welding of the joints
  • Ready to irrigate once the pump arrives
Another supply main — Agro MM2

Another supply main — Agro MM

Agro MM

A new supply main from HDPE pipes for Agro MM — delivery of the pipes, butt welding and laying across the fields. The site is in progress.

  • Supply main from HDPE pipes
  • Delivery of the pipes on site
  • Butt welding and laying of the main
  • The site is in progress
Laying a water main — Malo Konare2

Laying a water main — Malo Konare

Malo Konare

Construction of a new water main near Malo Konare — butt-welded HDPE strings, trench excavation and laying the main across the fields. The site is in progress.

  • Butt welding of HDPE pipes into long strings
  • Trench excavation for the main
  • Laying the main across the fields
  • The site is in progress
Ø280 main for two systems — Agro MM5

Ø280 main for two systems — Agro MM

Agro MM

A new supply main for Agro MM feeding two irrigation systems — 1280 m of Ø280 HDPE pipe, butt-welded and laid in 4 days. The water is taken from an irrigation canal via a reinforced-concrete intake structure.

  • Supply main from Ø280 HDPE pipe
  • Total length 1280 m
  • Feeds two irrigation systems
  • Completed in 4 days
  • Reinforced-concrete water intake from an irrigation canal
New Ø315 main — Agro MM3

New Ø315 main — Agro MM

Agro MM

Construction of a new supply main for Agro MM — 864 m of Ø315 HDPE pipe, butt-welded and laid in two and a half days. The first of four fields in the project.

  • Supply main from Ø315 HDPE pipe
  • Total length 864 m
  • Butt welding and laying of the main
  • Completed in two and a half days
  • First of four fields in the project
Laying a water main — Konyovo13

Laying a water main — Konyovo

Konyovo

Construction of a new water main near Konyovo — butt-welded HDPE strings, trench excavation and laying the main across the fields. The site is in progress.

  • Butt welding of HDPE pipes into long strings
  • Trench excavation for the main
  • Laying the main across the fields
  • Electrofusion welding of fittings and flanged joints
  • The site is in progress
Water main, pivots & pump station — Elit 2095, Popovitsa14

Water main, pivots & pump station — Elit 2095, Popovitsa

Popovitsa

Elit 2095

Construction of a new water main for Elit 2095 in Popovitsa. The linear section: butt-welded and laid HDPE mains — Ø280 — 645 m, Ø160 — 370 m and Ø125 — 708 m, delivered in 5 days. Centre pivots are connected to the main and a pump station with Grundfos pumps and a reservoir has been built. The system is ready to irrigate.

  • Water main from HDPE pipes, butt welding
  • Ø280 — 645 m
  • Ø160 — 370 m
  • Ø125 — 708 m
  • Linear section completed in 5 days
  • Connection of centre pivots to the main
  • Pump station with Grundfos pumps and a reservoir
Start of a new Ø355 supply main7

Start of a new Ø355 supply main

Start of a new supply main from Ø355 HDPE pipes — delivery of the pipes, butt welding into long strings and pulling/laying across the fields. The site started before Christmas and is in progress.

  • Supply main from Ø355 HDPE pipes
  • Butt welding of the pipes into long strings
  • Pulling and laying the main across the fields
  • The site is in progress
New supply main — Enfo Agro OOD7

New supply main — Enfo Agro OOD

Enfo Agro OOD

Preparation and laying of a new supply main for Enfo Agro OOD — delivery of HDPE pipes, butt welding into long strings and laying the main across the farmland. The site is in progress.

  • Delivery of HDPE pipes for the supply main
  • Butt welding of the pipes into long strings
  • Laying the main across the farmland
  • Preparation for connecting the irrigation system
Supply main from a reservoir & centre-pivot system — Ravna gora13

Supply main from a reservoir & centre-pivot system — Ravna gora

Ravna gora

Construction of a supply main with a water intake from a reservoir, feeding a centre-pivot irrigation system — butt welding and laying of HDPE pipes, pulling the main through the fields, supply of pumps and a diesel generator, and installing the pivot with shut-off valves. The site is complete.

  • Water intake from a reservoir and supply main
  • Butt welding and laying of HDPE pipes
  • Pulling the main through the fields
  • Supply of pumps and a diesel generator for the pump station
  • Pivot centre installation with shut-off valves
Water main for hose-reel irrigators — Bozduganovo10

Water main for hose-reel irrigators — Bozduganovo

Bozduganovo

Construction of a water main feeding hose-reel irrigation machines for farmland — laying HDPE pipes with branch connections and nodes.

  • Water main for hose-reel irrigation machines
  • HDPE pipe laying with butt and electrofusion welding
  • Branch connections and nodes for the irrigators
  • Farmland, Bozduganovo
Installation of a Ø500 outlet pipe — Debar dam6

Installation of a Ø500 outlet pipe — Debar dam

Debar dam, Parvomay area

Installation of a Ø500 outlet (discharge) pipe at the Debar dam — pipe laying with flanged connections, a shut-off valve and an air valve.

  • Installation of a Ø500 outlet pipe
  • Flanged connections and shut-off valve
  • Air valve installation
  • Site: Debar dam, Parvomay area
Drip irrigation for 1,000 dka of orchards — Bulgarevo8

Drip irrigation for 1,000 dka of orchards — Bulgarevo

Bulgarevo

Construction of a drip irrigation system for orchards totalling 1,000 dka (decares) near Bulgarevo — supply mains, a water intake node and shut-off valve assemblies.

  • Drip irrigation system for orchards
  • Irrigated area: 1,000 dka
  • Supply mains with fittings and shut-off valves
  • Water intake node and valve assemblies
Pump installation at the pivot — LenovoStage 64

Pump installation at the pivot — Lenovo

Lenovo

Enfo Agro OOD, Lenovo

Installation of a pump at the pivot centre — connection to an HDPE manifold with shut-off valves and flanged joints, with electrofusion welding of the pipes.

  • Pump installation at the pivot centre
  • Connection to an HDPE manifold
  • Shut-off valves and flanged joints
  • Electrofusion welding of the pipes
Irrigation system in operation — LenovoStage 510

Irrigation system in operation — Lenovo

Lenovo

Enfo Agro OOD, Lenovo

The completed irrigation system is in full operation — the centre-pivot machines are watering the maize fields, the pump station is running and the water intake feeds the mains. The result of every stage of the site.

  • Centre-pivot machines in operation
  • Running pump station with a frequency converter
  • Water intake feeding the mains
  • Irrigation of the maize fields
Tap-in from Ø400 asbestos-cement pipes & joining the mains — LenovoStage 43

Tap-in from Ø400 asbestos-cement pipes & joining the mains — Lenovo

Lenovo

Enfo Agro OOD, Lenovo

A branch from two Ø400 asbestos-cement (eternit) pipes and joining of the two mains to feed drip irrigation. The system is ready for the pivots in the autumn.

  • Branch (tap-in) from two Ø400 asbestos-cement pipes
  • Joining of the two mains into a common manifold
  • Installation of shut-off valves
  • Preparation for drip irrigation supply
Pivot assembly & start-up — LenovoStage 314

Pivot assembly & start-up — Lenovo

Lenovo

Enfo Agro OOD, Lenovo

Assembly of centre-pivot irrigation machines on the completed foundations and commissioning. The site is complete.

  • Assembly of centre-pivot irrigation machines
  • Span assembly and connection to the supply main
  • Pump station with shut-off valves
  • Commissioning — the pivots are irrigating
Pivot foundations — LenovoStage 27

Pivot foundations — Lenovo

Lenovo

Enfo Agro OOD, Lenovo

Construction of reinforced-concrete foundations for centre-pivot irrigation systems — excavation, formwork, reinforcement and concreting.

  • Reinforced-concrete foundations for pivots
  • Excavation, formwork and reinforcement
  • Concreting of the foundations
  • For centre-pivot irrigation systems
DN250/DN160 supply main & pump station — Lenovo3

DN250/DN160 supply main & pump station — Lenovo

Lenovo

Enfo Agro OOD, Lenovo

Supply and installation of pipes, fittings and shut-off valves for a DN250/DN160 supply main with vertical branch connections for sprinkler and drip irrigation, together with the supply and commissioning of a 53 l/s pump with a frequency converter.

  • Supply and installation of pipes, fittings and shut-off valves
  • DN250 supply main — 420 m
  • DN160 supply main — 480 m
  • 2 vertical branch connections for sprinkler and drip irrigation
  • Supply and commissioning of a 53 l/s pump with a frequency converter
Supply main for sprinkler irrigation systems — DN225 / DN200 / DN1808

Supply main for sprinkler irrigation systems — DN225 / DN200 / DN180

Ekvator EOOD, Burgas

Supply and installation of pipes, fittings and shut-off valves to build a supply water main over 2.1 km long in three diameters, with vertical branch connections for sprinkler irrigation systems.

  • Supply and installation of pipes, fittings and shut-off valves
  • DN225 supply main — 996 m
  • DN200 supply main — 492 m
  • DN180 supply main — 696 m
  • 2 vertical branch connections for sprinkler irrigation systems
DN90 potable & fire-fighting water main — residential complex, Novi Han2

DN90 potable & fire-fighting water main — residential complex, Novi Han

Novi Han area

Gama Tech EOOD, Sofia

Construction of a DN90 potable and fire-fighting water main, 2,585 m long, for a new residential complex of 86 single-family houses, together with 86 service connections, shut-off valves, water-meter chambers and fire hydrants.

  • DN90 potable & fire-fighting water main — 2,585 m
  • 86 DN25 house service connections
  • Installation of shut-off valves and water-meter chambers
  • 7 fire hydrants
  • Serving a complex of 86 single-family houses
Floating water intake & pump start-up — SpasovoStage 48

Floating water intake & pump start-up — Spasovo

Spasovo

Dimo Dimov (registered farmer)

Construction of a floating reservoir intake and commissioning of the pumping system. The site is complete — the client is now irrigating.

  • Floating pontoon intake from the reservoir
  • Suction line to the pump station
  • HDPE butt welding and shut-off valve installation
  • Commissioning — the system is irrigating
Pump relocation — SpasovoStage 34

Pump relocation — Spasovo

Spasovo

Dimo Dimov (registered farmer)

Relocation of the pumping installation to a new position at the water source — dismantling, building a new suction line with shut-off valves and recommissioning.

  • Relocation of the pump to a new position
  • New suction line at the water source
  • Installation of shut-off valves
  • Recommissioning
DN200 supply main, 1,720 m — SpasovoStage 26

DN200 supply main, 1,720 m — Spasovo

Spasovo

Dimo Dimov (registered farmer)

Supply of pipes, fittings and valves and construction of a DN200 supply water main, 1,720 m long, connecting to existing sprinkler irrigation systems.

  • Supply of pipes, fittings and valves
  • Construction of a DN200 supply main — 1,720 m
  • 3 vertical branch connections
  • Connection to existing sprinkler irrigation systems
DN200 supply main for a sprinkler irrigation system — SpasovoStage 17

DN200 supply main for a sprinkler irrigation system — Spasovo

Spasovo

Dimo Dimov (registered farmer)

Supply of HDPE pipes and construction of a DN200 supply water main, 1,200 m long, feeding a sprinkler irrigation system, together with inspection chambers and shut-off valves.

  • Supply of DN200 HDPE pipes
  • Construction of a DN200 supply main — 1,200 m
  • 3 inspection chambers
  • Installation of shut-off valves
Water mains & trenchless crossings — Elin Pelin – Kostenets railway section2

Water mains & trenchless crossings — Elin Pelin – Kostenets railway section

Mirovo, Ihtiman municipality

GP Group AD, Sofia

Relocation of an existing potable-water main and construction of a new fire-fighting pipeline for Tunnel No. 3, together with inspection and special chambers and two horizontal directional drillings for the trenchless crossing of the active Sofia – Burgas railway line.

  • Relocation of a DN160 potable-water main — 355 m
  • DN70 fire-fighting pipeline for Tunnel No. 3 — 411 m
  • 4 inspection chambers, 2 air-valve chambers, 1 water-meter chamber and 1 drain chamber
  • Installation of shut-off valves
  • 2 horizontal directional drillings DN300 and DN400 with casing pipes crossing the Sofia – Burgas railway line

Want a project like this?

Briefly describe the site — we'll come back with a quote within a business day.